Win IT Exam with Last Dumps 2024


CompTIA PK0-004 Exam

Page 35/43
Viewing Questions 341 350 out of 430 Questions
81.40%

Question 341
Based on the table below, Which of the following is the float of Task B?
Image PK0-004_341Q.png related to the CompTIA PK0-004 Exam
A. -2
B. 0
C. 2
D. 5

Question 342
Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?
A. Program evaluation review technique
B. Precedence diagramming method
C. Arrow diagramming method
D. Critical path method

Question 343
Based on the table below, Which of the following is the total float for the critical path?
Image PK0-004_343Q.png related to the CompTIA PK0-004 Exam
A. 0
B. 1
C. 2
D. 3

Question 344
An active construction project must make immediate changes when it is discovered that the designated project area contains protected wetlands.
Which of the following is the MOST likely impact to the project?
A. The project quality will decrease
B. The project scope will decrease
C. The project timeline will increase
D. The interproject dependencies will increase

Question 345
A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this situation?
A. Norming
B. Performing
C. Forming
D. Storming


Question 346
Which of the following primary factors are used to prioritize the development of risk response strategies? (Choose two.)
A. Likelihood
B. Timeline
C. Impact
D. Quality
E. Cost

Question 347
Which of the following job roles is MOST responsible for providing input on the project requirements, steering the project, providing expertise, and having vested interest in the project?
A. Project scheduler
B. Project stakeholder
C. Project team
D. Project coordinator

Question 348
Which of the following project phases occurs when requirements are detailed?
A. Initiation
B. Monitor and control
C. Planning
D. Closing

Question 349
Which of the following documents will provide the MOST detailed information regarding the work a vendor will perform during a project?
A. RFI
B. SLA
C. SOW
D. PO

Question 350
A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?
A. Analyze the critical path and update the WBS with the new feature
B. Add the new feature and reprioritize the product backlog
C. Add the new feature to the next sprint and move the old feature to the following sprint
D. Conduct a retrospective with the team to discuss the change and introduce the feature