A stakeholder is unaware of a project's status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of p...


CompTIA PK0-004 Exam

Questions Number: 9 out of 430 Questions
2.09%

Question 9
A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)