There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks - A, B, F: 8 weeks - D, E, H: 12 weeks - D, B,...
CompTIA PK0-004 Exam
Questions Number: 10 out of 430 Questions
2.33%
Question 10
There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks - A, B, F: 8 weeks - D, E, H: 12 weeks - D, B, F: 7 weeks - Which of the following tasks are on the critical path?