There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks - A, B, F: 8 weeks - D, E, H: 12 weeks - D, B,...


CompTIA PK0-004 Exam

Questions Number: 10 out of 430 Questions
2.33%

Question 10
There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks -
A, B, F: 8 weeks -
D, E, H: 12 weeks -
D, B, F: 7 weeks -
Which of the following tasks are on the critical path?