Win IT Exam with Last Dumps 2024


CompTIA PK0-004 Exam

Page 31/43
Viewing Questions 301 310 out of 430 Questions
72.09%

Question 301
A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?




Question 302
Given the following sprint:
Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?
Image PK0-004_302Q.png related to the CompTIA PK0-004 Exam




Question 303
When developing a project schedule, which of the following tools would be MOST beneficial?




Question 304
Based on the table below, Which of the following is the critical path if Task B has extended to ten days?
Image PK0-004_304Q.png related to the CompTIA PK0-004 Exam




Question 305
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?





Question 306
Which of the following charts is a mathematical diagram used to display values for two variables for a set of data?




Question 307
Expenditure tracking helps with cost:




Question 308
On an OBS chart, there is a dashed line between some team members and the project manager, and there is a solid line connecting other members to the project manager. Additionally, some employees at a lower level on the chart have no connection to the project manager.
Which of the following does this signify?




Question 309
A project manager is determining a project's critical path to report the projected completion date to stakeholders.
Which of the following information will be required? (Choose two.)




Question 310
A project manager has developed the initial schedule for an upcoming project.
Using the attached schedule, which of the following is the critical path?
Image PK0-004_310Q.png related to the CompTIA PK0-004 Exam