A diagram or chart is required to illustrate data differences given the following: 1. The diagram or chart must track at least two variables to determine the relationship between independent variables and include a regression or trend line. 2. The diagram or chart should include cause and effect analysis and investigate historical information. Which of the following should be used given these requirements?
Question 312
During the planning phase, the project manager meets with the project team to determine the tasks and their relationship. Which of the following should the project manager receive from the team members? (Choose two.)
Question 313
Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members. Which of the following steps should the PM take to make the meetings more productive? (Choose two.)
Question 314
A project team is identifying, rating the probability of, and determining the impact on potential problems throughout the project. The team is also including the corresponding actions to take. Which of the following activities does this describe?
Question 315
A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?
Question 316
Given the information in the table below, which of the following is the total project cost?
Question 317
The design team and development team disagree about what technology should be used for a major requirement. A brainstorming meeting takes place, where both teams focus on the mutually agreed-upon deliverables. Which of the following conflict resolution techniques did the teams use?
Question 318
A project manager is analyzing the cost variances produced when comparing two different projects completions. Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)
Question 319
One of the tasks on a project's critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive deadlines. Which of the following roles has the responsibility of resolving the issue?
Question 320
A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeting is taking too long and not providing summary information on the project's progress. Which of the following should the project manager be presenting?