Question 241
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?




Question 242
Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?




Question 243
Which of the following defines the minimum level of engagement of a stakeholder?




Question 244
At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?




Question 245
A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?





Question 246
A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?




Question 247
A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial.
This would likely impact the project's: (Choose two.)




Question 248
Which of the following information does the project risk register typically contain?




Question 249
A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?




Question 250
A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?