Question 231
A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?




Question 232
Which of the following risk strategies prevents a risk from impacting a project?




Question 233
An active project has a CPI of 0.92. Which of the following can be determined?




Question 234
A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?




Question 235
A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations.
The project team must ensure completion of the:





Question 236
While developing a project schedule, the project manager is attempting to sequence the following tasks:
Which of the following is the correct sequence for the above tasks?
Image PK0-004_236Q.png related to the CompTIA PK0-004 Exam




Question 237
Which of the following represents additional unauthorized requirements from the client?




Question 238
A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?




Question 239
Which of the following describes KPIs?




Question 240
Before a team can start on a sprint, they will need to: