Question 301
A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?
A. Schedule the change
B. Review the communication plan
C. Update the issue log
D. Update the risk register

Question 302
Given the following sprint:
Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?
Image PK0-004_302Q.png related to the CompTIA PK0-004 Exam
A. Gantt chart
B. Pareto chart
C. Scatter chart
D. Burndown chart

Question 303
When developing a project schedule, which of the following tools would be MOST beneficial?
A. Gantt chart
B. Network diagram
C. Fishbone chart
D. Chain diagram

Question 304
Based on the table below, Which of the following is the critical path if Task B has extended to ten days?
Image PK0-004_304Q.png related to the CompTIA PK0-004 Exam
A. 21 days
B. 23 days
C. 24 days
D. 26 days

Question 305
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
A. RFP
B. RFQ
C. RFI
D. SOW


Question 306
Which of the following charts is a mathematical diagram used to display values for two variables for a set of data?
A. Histogram
B. Fishbone
C. Gantt
D. Scatter

Question 307
Expenditure tracking helps with cost:
A. reporting
B. scheduling
C. discounting
D. floating

Question 308
On an OBS chart, there is a dashed line between some team members and the project manager, and there is a solid line connecting other members to the project manager. Additionally, some employees at a lower level on the chart have no connection to the project manager.
Which of the following does this signify?
A. Horizontally aligned organization
B. Vertically aligned organization
C. Matrix aligned organization
D. Project aligned organization

Question 309
A project manager is determining a project's critical path to report the projected completion date to stakeholders.
Which of the following information will be required? (Choose two.)
A. Costs
B. Dependencies
C. Schedules
D. Durations
E. Holidays
F. Milestones

Question 310
A project manager has developed the initial schedule for an upcoming project.
Using the attached schedule, which of the following is the critical path?
Image PK0-004_310Q.png related to the CompTIA PK0-004 Exam
A. 12 days
B. 14 days
C. 16 days
D. 17 days