Win IT Exam with Last Dumps 2024


CompTIA PK0-004 Exam

Page 3/43
Viewing Questions 21 30 out of 430 Questions
6.98%

Question 21
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?
A. Business case
B. Requirements document
C. Project timeline
D. Task plan

Question 22
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?
A. A list of realized risks
B. A list of decomposed activities
C. A sequenced list of project tasks
D. A document describing agreed-upon communication methods

Question 23
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
A. Cost baseline
B. Burn rate
C. Cost variance report
D. Total project cost

Question 24
Which of the following defines a group of projects that work together to achieve a common goal?
A. Product
B. Portfolio
C. Program
D. Project plan

Question 25
A company hires an outside vendor to provide 24/7 support.
Which of the following documents would determine the contractual obligations?
A. PO
B. SLA
C. LOI
D. MOU


Question 26
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time?
A. Throttling
B. Crashing
C. Resource leveling
D. Resource smoothing

Question 27
A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?
A. Conduct a face-to-face or telephone meeting with the team member.
B. Send an email outlining the concerns to the team member.
C. Send a project team meeting to obtain feedback from everyone.
D. Post the issue on the wiki page for input from stakeholders.

Question 28
Which of the following is a key aspect of the Agile project management methodology?
A. Test-driven
B. Daily standup meetings
C. Short project durations
D. Defined list of requirements

Question 29
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
A. Assess the risk register's new items.
B. Review the task start and finish dates.
C. Obtain additional resources.
D. Analyze the assigned hours.

Question 30
A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements.
Which of the following actions would be BEST for the project manager to take?
A. Ask the client to provide additional language resources to the team.
B. Purchase a language translation program.
C. Hire a translator to help the key team member
D. Ask the client to provide requirements in the native language of the team.