Question 281
Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
A. Pie chart
B. Run chart
C. Project schedule
D. Dashboard information

Question 282
A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.
The constraint described in this scenario is:
A. cost
B. environmental
C. scope
D. scheduling

Question 283
A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.
Which of the following steps of the control was missed?
A. Communicate the change
B. Quality check
C. Implementation
D. Evaluate impact and justification

Question 284
Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.
Which of the following management styles is the project manager MOST likely using?
A. Exploitive
B. Retrospective
C. Participative
D. Authoritative

Question 285
Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.)
A. Planned value
B. Schedule variance
C. Acceptable variance
D. Cost variance
E. Earned value


Question 286
The project manager needs to motivate the team; however, there is an insufficient budget for awards.
Which of the following motivating agents is the MOST appropriate option the project manager can utilize?
A. Reduce the workload
B. Replace resources
C. Extend the timeline
D. Provide additional responsibility

Question 287
A project manager needs status on the project timeline.
Which of the following team members should provide an update?
A. Product owner
B. Business analyst
C. Scheduler
D. Sponsor

Question 288
A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays.
Which of the following is the BEST risk response strategy?
A. Exploit
B. Enhance
C. Mitigate
D. Communicate

Question 289
Under an Agile methodology, standup meetings occur:
A. daily
B. twice daily
C. weekly
D. ad hoc

Question 290
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are MOST likely missing from the project? (Choose two.)
A. Project charter
B. Organizational chart
C. Scope document
D. Status report
E. Business case
F. Project plan