Question 411
While planning a project, the project team estimates known expenses but also applies a margin of error for unknown expenses. Which of the following is the project team trying to determine?




Question 412
A project facilitator is working within a large project team that includes 36 members representing different organizational groups. The current communications plan calls for full status updates to be emailed to the whole group twice per week. Which of the following factors should be considered FIRST when communicating with this group?




Question 413
A project manager creates a Pareto chart based on the table below, Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and faulty installation?
Image PK0-004_413Q.png related to the CompTIA PK0-004 Exam




Question 414
Rather than sending emails to communicate all project information, the project manager:
- Makes telephone calls to key stakeholders for urgent information
- Sends emails for routine information
- Posts on the project intranet site for required but minimally used information
Which of the following BEST represents what the project manager is doing?




Question 415
A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response. The memo that prompted the activation of the risk response is referred to as the:





Question 416
When a project team member completes a task in the WBS, which of the following are the primary recipients of the notification? (Choose two.)




Question 417
Company A and Company B have come together to form a new Company C. Staff members from both companies have been moved to Company C, and there are rumors that some staff might be asked to leave. These are examples of: (Choose two.)




Question 418
Which of the following project roles is ultimately responsible for all project artifacts?




Question 419
A project team has just finished one phase of product development and is gathering requirements for the next phase. Which of the following methodologies is being applied?




Question 420
Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following types of communication is BEST in this event?