The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy. Based on the following entry: Which of the following should be modified to BEST eliminate confusion?
Question 372
In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?
Question 373
Which of the following should be included in an effective SOW?
Question 374
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
Question 375
The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project's success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?
Question 376
Which of the following documents are considered mutually binding? (Choose two.)
Question 377
A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to the sponsor to quickly identify the project activities?
Question 378
Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
Question 379
A project manager is reviewing project performance. Which of the following would be the BEST indicator of the total project cost?
Question 380
According to the communication management plan, the project scheduler is required to post weekly status reports on the project's intranet site. From the stakeholders' point of view, accessing the weekly report is an example of: