Win IT Exam with Last Dumps 2024


CompTIA PK0-004 Exam

Page 34/43
Viewing Questions 331 340 out of 430 Questions
79.07%

Question 331
A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer (CEO) directs that all meetings be conducted via video conference to save costs and expedite communication. This scenario is an example of:




Question 332
A company's management team is in a meeting to review all the products and services delivered in the first quarter of the year for profitability. They are requesting information on payback period, return on investment, and total cost of ownership. The project manager is checking the project repository for available documentation. In which of the following documents is the project manager MOST likely to find the required information?




Question 333
A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance.
Which of the following should the PM do NEXT?




Question 334
A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?




Question 335
Which of the following make up a company's portfolio? (Choose two.)





Question 336
A recently added stakeholder is unaware of critical changes that will affect the department. Which of the following should the project manager do FIRST to ensure all parties have the same level of information?




Question 337
A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO), the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?




Question 338
Which of the following resources outlines consequences of non-performance?




Question 339
During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:




Question 340
An organization wants assurance that the specialty tools necessary for operation will function as intended for a specific minimum time period. Which of the following documents BEST provides this assurance?