Question 211
A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?




Question 212
Which of the following is used to perform a root cause analysis?




Question 213
Which of the following documents is typically signed by the vendor and includes a reference for how customers' internal information will be protected?




Question 214
A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?




Question 215
A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?





Question 216
A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?




Question 217
During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:




Question 218
A project manager procures additional resources from a local company. Which of the following-describes this event?




Question 219
In which of the following situations is a project manager MOST likely to use a process diagram?




Question 220
A project has passed a phase-gate, and the new phase is ready to begin. Which of the following is the MOST appropriate method to communicate the transition to team?