Win IT Exam with Last Dumps 2024


CompTIA PK0-004 Exam

Page 20/43
Viewing Questions 191 200 out of 430 Questions
46.51%

Question 191
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:




Question 192
The project team is not comfortable moving an expensive material.
A third party is hired to move the material. This is an example of risk:




Question 193
The project's network map has a loop with multiple project outcomes.
This is the result of which of the following scheduling tools?




Question 194
Which of the following tools would a project manager use to determine the root cause of an issue?




Question 195
Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?





Question 196
Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?




Question 197
A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?




Question 198
Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?




Question 199
A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?




Question 200
A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.
Which of the following represents the cost variance for both project completions?
Image PK0-004_200Q.png related to the CompTIA PK0-004 Exam