Question 161
A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:




Question 162
A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?




Question 163
A project has a ׀’׀׀¡ of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager doNEXT?




Question 164
A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?




Question 165
A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project.
Which of the following MOST likely occurred?





Question 166
In which of the following categories does a business process change fit?




Question 167
A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon.
Which of the following is the BEST explanation?




Question 168
A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is theMOST likely reason for the failed inspection?




Question 169
A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?




Question 170
A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?