Question 141
A team member has completed an assigned task. Which of the following roles should be notified FIRST?




Question 142
A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?




Question 143
A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?




Question 144
Using Scrum, which of the following are discussed in a daily standup meeting?




Question 145
A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.
Which of the following calculations accurately shows the critical path?
Image PK0-004_145Q.png related to the CompTIA PK0-004 Exam





Question 146
׀ new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?




Question 147
A project manager has been asked to prepare and present a review of the execution phase.
Which of the following is the BEST audience for this review?




Question 148
Which of the following inherently affects quality standards?




Question 149
At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?




Question 150
A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?