You need to consider the underlined segment to establish whether it is accurate. The Burnup widget measures the elapsed time from creation of work items to thei...


Microsoft AZ-400 Exam

Questions Number: 3 out of 535 Questions
0.56%

Question 3
You need to consider the underlined segment to establish whether it is accurate.
The Burnup widget measures the elapsed time from creation of work items to their completion.
Select `No adjustment required` if the underlined segment is accurate. If the underlined segment is inaccurate, select the accurate option.



Reference:
https://docs.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead-time?view=vsts